Award-winning Apartments
Sölden BrochureOetz Brochure‏Kühtai Brochure‏St Anton Brochure‏

St Anton construction news

22 June: in Haus A, the structure of the indoor swimming pool and spa area is now in place thanks to many lorry loads of concrete.

20170626_Mountain_Spa_Residences

[Click image to enlarge]

Next we will complete the ground floor which contains the brasserie and bar area and the ground floor apartments. Meanwhile in Haus B, the wood cladding is being fitted and plastering has begun. 

1 June: with over 100 people on-site in St Anton, building continues at pace.  In Haus B, the underfloor heating is in place and the screed laid.  The photo below is taken from the second floor balcony in Haus B.  We expect to have a show apartment ready for customers to view in the next 2 months.  Right now, buyers can walk round the floors and apartments in Haus B.  Haus A will be at a similar stage by the end of July.

st anton 29 May

19 May: Good progress being made in St Anton. We currently have 80 people on site and 2 cranes. The first fix is completed in Haus B and the concreting for the underground parking is under way in Haus A. We will see progress happening very quickly in Haus A and it won’t be long until the next floor is in place.

28 April: We are back to business on the building site in St Anton.  The cranes have been erected and we are working on the interiors of Haus B and its plumbing.  Haus A concreting to commence imminently. 

2 April 2017: As soon as the lifts stop running, construction will continue in earnest on the Baustelle.  We will go on site with 3 cranes on 24 April and will be using prefabricated materials to make rapid progress on Haus A.  We expect prospective owners will be able to walk around all Haus A apartments by the end of July.  Completion date is November 2017.

1 Dec: We are pleased to announce we have topped out and weather proofed Building B in St Anton as planned before the ski lifts start for the winter season this week.  The foundation work and the retention system for Building A is now completed so we can hit the ground running in the New Year for completion in the late Autumn.

7 Nov: Lots of snow in St Anton but work continues. The roof will go on in Haus B in before the end of the month and we will carry on with the foundations in Haus A.

28 October: the third floor is now in place in Haus B and the foundations are ready for concrete in Haus A.  Some great views up and down the valley.

4 October 2016: the underground floor is now complete in Haus B and we are finishing the first floor with its supporting walls for the second floor.   At the same time, the foundations of Haus A are being excavated.

7 September 2016: 36 tonnes of steel in use in the roof of the underground parking in Haus B.  Next comes more concrete.

25 July 2016: crane now on-site for the construction to start; all the concrete sections are in place and waiting for concrete pouring.

st anton 26 july

12 July 2016: the excavation of Haus B is now complete and the teams will move in next week to start the foundations.

facebook_1468389598823

1 July 2016: major excavation underway in Nasserein.  Keep checking back to follow progress.

23 June 2016: major excavation work is taking place in Nasserein at the site of the future Mountain Spa Residences – St Anton.

IMG_1286

We look forward to bringing you regular updates as we progress this exciting project to build arguably the most sophisticated ski apartments in the Alps.

29 February 2016: Whilst all is seemingly quiet on the building site in Nasserein, there’s a lot of work going on with the developers and their partners.

Right now, detailed drawings plans (Ausführung Plane) are being continually refined with the building engineers and fed into the construction plans.

At the same time, we are completing the tendering processes for local firms and craftsmen to supply the heating, plumbing, electrics and joinery.  We will use as many Tirolean or Austrian firms as possible with the notable exception of ceramics in which case we prefer to work with Italian suppliers.

Crossing the fields and heading towards the Nassereinbahn:

4 December: if you are visiting St Anton these holidays then please do arrange to meet with one of our bi-lingual representatives in Nasserein at 15, Ing.-Gomperz-Weg 15 (the site of the old Hotel Schweizerhof)  Google Map location https://goo.gl/maps/2uar2vK3V7T2

sign

We would be delighted to discuss the new Mountain Spa Residences, St Anton with you in person.

12 November: the Hotel Schweizerhof is no more as the team gets into gear on the construction of the new Mountain Spa Residences, St Anton.

Mountain Spa Residences St Anton

Please keep checking back as we progress with the building phases of these luxury apartments and 600m2 wellness including two swimming pools (one indoor and one outdoor).

St Anton real estate

28 October: another sunny day in St Anton and the last few days of the Hotel Schweizerhof being dismantled in the peaceful surroundings of Nasserein.  Below is the view to the West with the Nassereinbahn below in the foreground and the resort behind.  It produces some of the best sunset views in the valley thanks to its high vantage point.

St Anton property for sale - Kristall Spaces

Please view our video taken from the air and imagine putting your skis on outside your own apartment to ski down and across the alpine meadows past the stadls towards the Nassereinbahn from the Mountain Spa Residences – St Anton.

18 October: a beautiful day on the Baustelle in St Anton as the Hotel Schweizerhof  continues its transformation into the Mountain Spa Residences – St Anton.

4 October: Kristall Spaces is delighted to announce the beginning of construction of the Mountain Spa Residences – St Anton.

St Anton property for sale - Kristall Spaces

The current Hotel Schweizerhof in Nasserein is being demolished to make way for two principal buildings with underground parking and 600m2 wellness including two swimming pools (one indoor and one outdoor).

Immobilien in St Anton - Kristall Spaces